  1. HD_ACE

    Getting DA and cancelling the building contract

    Actually the point of difference is I had a drafty do my plans and then submitted DA to council. Then tendered plans to builders for price. Chosen builder then did working drawings after signed ppa.
  2. HD_ACE

    Getting DA and cancelling the building contract

    Hi Tano From my experience it went concept drawings > da approval from council ( 6-12 weeks) > ppa agreement and deposit for working drawings (upto 90 days) > building permit from council.