    Thats the generall timeframe all going well. If council or any of the public object or its outside of the r-codes etc then it will take longer.
  2. HD_ACE

    development advice

    Not sure on the size of that lot but would look something like this 1 month for survey and to be lodged to wapc 3 months at least at wapc for conditional approval 1-3 months to meet conditions ie western power, watercorp, roads/crossovers etc 1 month for approval 2 months for titles...
  3. HD_ACE

    development advice

    Then your best bet would be a surveyor. Vision surveys I have used are good so maybe give them a try. They have a project management side to guide you through the whole process from survey to titles if that is what you are after.
  4. HD_ACE

    development advice

    Just subdivision and sell the land? or house and land packages or selling the completed product?
  5. HD_ACE

    development advice

    So a project manager? What sort of development/size and type are you talking?