    Can I sue our Builder for not finishing our IP in time

    2-3 months is expecting a bit much I think. Normal building contract period here in sydney is 26 weeks 6 months Liquidated Damages in the HIA building contract is somethig like $5-$10 per day. Hardly worth it. If your builder has used a std HIA or similar contract it usually favours the...