Hi there,
I am looking at undertaking an extensive renovation including extra level, additional garage, pool, changes to facade and potential lift access.
Can someone run me down the pros and cons of Private Certify vs Council Development Application approval. The council is Manly Council, NSW - on I guess a more "prestigious" street.
1. Am I right in saying that simply if the plans can be approved by Private Certifier, then this is definitely the route to go down with?
2. If only some items can be approved by the Private Certifier, can I simutanously submit to council DA other elements of the wish list/renovations?
3. What is the best way to find a lenient Private Certifier or are they all the same?
4. With the Council DA you have 4 years to make a substantial start on the works, then the there is no time limit on the completing the building work. Is this the same with the Private Certifier route?
I am looking at undertaking an extensive renovation including extra level, additional garage, pool, changes to facade and potential lift access.
Can someone run me down the pros and cons of Private Certify vs Council Development Application approval. The council is Manly Council, NSW - on I guess a more "prestigious" street.
1. Am I right in saying that simply if the plans can be approved by Private Certifier, then this is definitely the route to go down with?
2. If only some items can be approved by the Private Certifier, can I simutanously submit to council DA other elements of the wish list/renovations?
3. What is the best way to find a lenient Private Certifier or are they all the same?
4. With the Council DA you have 4 years to make a substantial start on the works, then the there is no time limit on the completing the building work. Is this the same with the Private Certifier route?