Hi All,

I'm just wondering if anyone has a spreadsheet for a project management run sheet. Etc the order from start to finish for a development or renovation, when to get each trade in. Or like a scope of works for the job.

Sorry if this was posted in the wrong section.
 
Surveyor
Earthworker
Surveyor
Footings
Plumb/Elect Prelay
Pest treatment
Slab pour
Soakwells
Plumb drains
Elect mains run
Load brick/frame materials.
Brickwork
Roof Carpenter
Roof plumber
Elect/Plumb tube out
Roof Cover
Ducted Air Con (if req.)
Plaster float
Ceilings
Plaster Set
Doors/glazing lockup
Painter spray out (ceilings/doors/sealing)
Sani plumbing
Cabinets
Tiler
Plumb finals
Shower screens/mirrors
Elec finals (need screens in for ticketing of job).
Insulation
Paint finals.
Stormwater pipe-in
Final pest treatment
Garage hardstand
Roller Door install
Carpets/blinds/paving/landscaping etc.


See, easy (above relates to typical construction of single storey in WA).
 
This is awesome!

Couldn't have put it better myself

Surveyor
Earthworker
Surveyor
Footings
Plumb/Elect Prelay
Pest treatment
Slab pour
Soakwells
Plumb drains
Elect mains run
Load brick/frame materials.
Brickwork
Roof Carpenter
Roof plumber
Elect/Plumb tube out
Roof Cover
Ducted Air Con (if req.)
Plaster float
Ceilings
Plaster Set
Doors/glazing lockup
Painter spray out (ceilings/doors/sealing)
Sani plumbing
Cabinets
Tiler
Plumb finals
Shower screens/mirrors
Elec finals (need screens in for ticketing of job).
Insulation
Paint finals.
Stormwater pipe-in
Final pest treatment
Garage hardstand
Roller Door install
Carpets/blinds/paving/landscaping etc.


See, easy (above relates to typical construction of single storey in WA).
 
Ok thanks for your replies and advice.

Use that list as a guide. WA build a little differently. Also, as you probably know, each development differs so take that into account too.

I have my own Call Sheet. If you want a copy shoot me a PM.
 