G'day all,
A question on schedule for house construction, actually the timing of the 5 stages : Base, Frame, Lock-up, Fixing, Completion.
Assuming completion is at 285 days where would the others fit in ?
day 000 : Start
day ? : Base
day ? : Frame
day ? : Lock-Up
day ? : Fixing
day 285 : Completion
I realise there are many factors that can delay or put the whole schedule out, but here I'm just after the overall plan.
All input welcome.
A question on schedule for house construction, actually the timing of the 5 stages : Base, Frame, Lock-up, Fixing, Completion.
Assuming completion is at 285 days where would the others fit in ?
day 000 : Start
day ? : Base
day ? : Frame
day ? : Lock-Up
day ? : Fixing
day 285 : Completion
I realise there are many factors that can delay or put the whole schedule out, but here I'm just after the overall plan.
All input welcome.