We were asked by our builder to sign an amendment to the development application because the finished floor level is lower than the approved plans.
Problem is they only sent us the last page of the application (where the signature goes) and didn't send the whole of application filled. We're asking for the whole document.
We had problems with them adding and deleting things to the construction plans. E.g deleting some feature bricks, deleting croosover, adding infill panels above windows.
We don't want to sign anything that'll allow them to make whatever changes they want to the revised plans.
Question is, is lodging an amendment normal for finished floor level?
Also can they add or delete things to the construction plans without our approval?
Is it time to consult legal advice. Will need recommendations.
Problem is they only sent us the last page of the application (where the signature goes) and didn't send the whole of application filled. We're asking for the whole document.
We had problems with them adding and deleting things to the construction plans. E.g deleting some feature bricks, deleting croosover, adding infill panels above windows.
We don't want to sign anything that'll allow them to make whatever changes they want to the revised plans.
Question is, is lodging an amendment normal for finished floor level?
Also can they add or delete things to the construction plans without our approval?