Would appreciate any advise/views on this:
We have a project planned to start in early January 2014 and have tentatively booked demolition of existing property mid December.
We gave the tenants who are on periodic lease and very/very low rent 90 days notice in mid September. The condition of the property is very poor but the tenants are finding it hard to find another property with similar rent where they can get approved.
Have spoken to PM and done my research and it appears we have to wait for the original 90 days notice to expire and if tenants have not moved out then we can go to the tribunal and get an order to evict the tenants.
So it may mean that even after the 90 days notice we have to take more time to get the tenants out.
We have a project planned to start in early January 2014 and have tentatively booked demolition of existing property mid December.
We gave the tenants who are on periodic lease and very/very low rent 90 days notice in mid September. The condition of the property is very poor but the tenants are finding it hard to find another property with similar rent where they can get approved.
Have spoken to PM and done my research and it appears we have to wait for the original 90 days notice to expire and if tenants have not moved out then we can go to the tribunal and get an order to evict the tenants.
So it may mean that even after the 90 days notice we have to take more time to get the tenants out.