I am wondering if there is anything we can do contractually to get builders/ trades to stick to our timelines? Naturally there are the unexpected and uncontrollable issues however, lets assume that whatever reason provided is 'BS' or i dont want to believe it.
How do we hold them accountable to our timelines? When they shift one day it may affect other trades, then those trades turn around and potentially shift it for another week and so on...
Is it possible to have an 'inconvenience' fee incorporated? After 3 business days after original set date, if works are not completed. We will deduct 10% off the total bill etc etc...
How do we hold them accountable to our timelines? When they shift one day it may affect other trades, then those trades turn around and potentially shift it for another week and so on...
Is it possible to have an 'inconvenience' fee incorporated? After 3 business days after original set date, if works are not completed. We will deduct 10% off the total bill etc etc...