I'm after a bit of help.
Story is builders grano worker stuffed the setout and the slab is short by 100mm on a few sections but was long on one wall. They also have reduced the internal measurements of my ensuite because of the slab being setout wrong. No variation here either just carried out works without telling me.They then cut 100mm off the slab only to realise that they now had only 50mm overhang on the footing.
Next they decided to cut another 300mm off to pour a new footing and re pour slab backout. All cuts were done without my knowledge and no variations have been offered.
Well it has been 4-5months of no work whatsoever because they can not find anyone to carry out the works to fix someone elses stuff up.
They now have until Dec to finish house as per the contract which in my opinion will not happen.
Can someone tell me what happens if a builder goes over the agreed time to complete the build?
Thanks for any help
Regrow
Story is builders grano worker stuffed the setout and the slab is short by 100mm on a few sections but was long on one wall. They also have reduced the internal measurements of my ensuite because of the slab being setout wrong. No variation here either just carried out works without telling me.They then cut 100mm off the slab only to realise that they now had only 50mm overhang on the footing.
Next they decided to cut another 300mm off to pour a new footing and re pour slab backout. All cuts were done without my knowledge and no variations have been offered.
Well it has been 4-5months of no work whatsoever because they can not find anyone to carry out the works to fix someone elses stuff up.
They now have until Dec to finish house as per the contract which in my opinion will not happen.
Can someone tell me what happens if a builder goes over the agreed time to complete the build?
Thanks for any help
Regrow