I'm glad it came through, but now you know better than to believe the time lines they tell you.
They too live in the fantasy that they actually do their job.
When in reality their is no rush to them. They get paid at the end of the week anyway.
At the end of the project I will write a letter to the council.
This afternoon we had coffee with a friend and she has a little nifty machine that cuts out letters and numbers so our friend will make our Owner Builder sign to go up on the block.
This week we will go to council and pay Section fees $18,981 and clarify when Construction Certificate will be available
Will also pay Building under construction insurance.
Running tab...
Land 145K (deposit 7K Loan 112K LOC 26K)
Stamp Duty to OSR $3420 + bank cheque $10
Structural Engineer $1980
HIA standard builder's contract, specifications & builders site board ? about $100
Owner Builder Permit $148
DA $7577
Section fees $18,981
Loan fees
-Bank cheque $20
-Mortgage registration fees $92
-Transfer/conveyance $184
-Stamp Duty $389
Lawyer fees
-$880
-Final search fees $10.01
- search& enquiry fees $152.90
- Online stamping fees $2.53
- Sundries & petties $77.00
Total
$179023.44
Sheryn