Site cost and engineering cost for multi unit in Perth

Hi all,

How much extra does clay come into play for site work and engineering cost? Is there a rough per sqm guide? The site is 2000+sqm big and I'm planning to put 1000sqm floor space of units on it (about 14-16 units).

In addition, the site currently has no sewage, and it is about 200m from the closest junction. I was inform that I could either run it to my block, which costs about $750/m, or I can install a plumbing station on site. Has anyone got experience with this?

I'm currently using a $190k per unit and $2500 per sqm as a cost guide but my gut feel is this may not be enough for this site.

Would be good to know what you guys think.

Thanks.

Regards
S
 